Value:
$1.5 million
Client:
Department of Education
Project Type:
Education
Brief Description:
The works consisted of a major refurbishment of the existing Level 9 space within the NIER Building A at the Callaghan Campus. The remaining floors of the building needed to remain operational whilst the works were completed to a strict deadline.
Works included:
- Removal of furniture, internal linings, floor coverings and services.
- Installation of new partitions, ceilings, floor coverings, joinery and workstations.
- New services including fire detection, air conditioning, AV equipment and energy efficient lighting.
- Replacement of the dilapidated roof sheeting with new.
Due to the fit out being on the top floor all major materials we moved using a hoist installed to temporary scaffolding on the external of the building.
Delivery Method:
Design & Construct
Contact Details:
Mr Callan Denny
Principle Project Management
The Junction NSW